National Road No.7 Improvement Project (ADB8)

Location: Moaung Phoukhoun - MoaungPhonsavanh in Xiengkhouang Province
Total Length of Roads : 298 Km
Width: Phoukhoun - Soui District = 5.50 m
Soui - Phonsavanh District = 6.50 m
Phonsavanh - Namkane District = 6.50 m
Phonsavanh - Phoukhoun District = 6.50 m
Construction Cost: USD 34,429,279
Type : Double Bitumen Surface Treatment
Funded by : ADB
Construction Supervision Period : Oct.1997 to Feb. 2002

This project was upgrading of the main road for all season accessible with DBST road pavement. Reconstruction and strengthening and improved drainage structures. Services included construction supervision to supervise on the progress of the Contractor's performance and quality of work etc.